Musical Theatro Oberhausen

Slipforming in 3 steps

Gleitbau Salzburg had only 2 months to complete the rough building phase. The stage area was slipformed in 2 phases and the semi-circular auditorium in one. The construction of the steeply inclined gables proved to be a particular challenge for the team.

Back

CountryGermany
Town / AreaOberhausen
Year of execution1999
Client / General contractorAugust Heine, Oberhausen
Height31,36 m
Surface10.204,65 m²