Sakhalin I Öl- and Gasplatform
Monday 16. May 2011 17:25
Year of execution: 2010/2011
Main Contractor / Client: Aker Solutions / Aker Advantage / Exxon Mobile
Country: Nakhodka / Russia
Construction of caissons and shafts for a GBS Oil- and Gasplatform.
In the first construction phase the caissons had been executed in 4 slipforming sequences (2010). In the second construction phase the 4 shafts are being executed (2011).
Dimensions of the construction:
Caissons:
Ground area: 100 x 132,6 m
Wall thicknesses: 0,50 / 0,75 / 0,40 / 0,65 / 0,85 m
Sliipforming height: 11.40 m
Total lm of slipform: 5.185 lm
Shafts:
Diameter: 25,80 m
Wall thicknesses: 0,85 / 0,90 / 0,98 m
Slipforming height: 41,20 m
Total lm slipform: 620 lm